Subcontractor EnerMech has won an appeal in its fight against Acciona over a $10 million progress payment for work on the Westconnex M4-M5 link, with an appeals court finding the question of whether EnerMech’s claim was a payment claim for construction work was a matter for an adjudicator, not the court.
Acciona has prevailed in a fight with subcontractor EnerMech over a $10 million progress payment, which a judge found was instead an attempt by EnerMech to claim a credit in relation to security paid to Acciona.
A judge has denied an application by industrial filter manufacturer Laminar Air Flow to add a new respondent in a long-running trade mark dispute against rival Vokes Ltd, with a judge finding the company had provided no explanation as to why the bid was made just four months before trial.